HomeMy WebLinkAboutEXECUTIVE SESSION - 08/16/2022 - LAND ACQUISITION (2)EXECUTIVE SESSION
August 16, 2022
6:40 p.m.
Chernick Conference Room
TOPIC: ❑ LITIGATION ❑ PERSONNEL X LAND ACQUISITION
VILLAGE BOARD
MEMBERS PRESENT
C. JOHNSON
Mayor
P. FEICHTER
Village Trustee
J. FRANKE
Village Trustee
S. LISSNER
Village Trustee
T. MILLER
Village Trustee
C. PROCHNO
Village Trustee
S. SCHMIDT
Village Trustee
VILLAGE BOARD
MEMBERS ABSENT
STAFF PRESENT
M. ROAN
Village Manager
M. JABLONSKI
Deputy Village Manager
C. GABIGA
Assistant Village Manager
D. STORINO
Acting Village Attorney
Pursuant to a duly made and approved motion and a majority vote at a regularly scheduled meeting
of the Mayor and Board of Trustees on August 16, 2022, this Executive Session was called to
consider review of Land Acquisition.
Number of pages attached:
Date(s) of review for release:
Date of approval for release:
Date approved by Village Board:
1
February 2024
September 13, 2022
August 16, 2022
6:40 pm
The Village has been working with Cook County and IDOT to acquire ownership of the Midway
Court right-of-way, which will facilitate the full build -out of the Prime Data Center
Development. The Village requested assistance from State Senator Laura Murphy and State
Representative Marty Moylan to encourage timely action by IDOT, who has had the Village's
request since February 2021.
Cook County owns part of the ROW, and the Village is concerned based on their comments that
they plan to value their parcel based on the price per square foot paid to Vulcan, which was
$70/sq. foot. This price included a substantial payment for Vulcan to agree to shut down their
operations, since no available relocation space could be found. Staff is working toward the
release of Midway Court from Cook County and IDOT.
The meeting was adjourned at 6:40 pm.