HomeMy WebLinkAboutCOMMITTEE OF THE WHOLE - 03/26/1991 - RESOURCE CENTER FOR ELDERLY/JFK BRIDGE RECONSTRUCTION COMMITTEE OF THE WHOLE
MEETING
3-26-9.1
7 P.M.
PRESENT:
C . Zettek, Village President
M. Tosto, Village Trustee
N. Czarnik, Village Trustee
J. Petri, Village Trustee
J. Bosslet, Village Trustee
R. Chernick, Village Trustee
D. Gallitano, Village Trustee
ABSENT:
NONE
,STAFF PRESENT:
C. Willis, Village Manager
G. Parrin, Assistant Village Manager
R. Rummel, Administrative Assistant
M. Pye, Assistant Village Engineer
G. Knickerbocker, Village Attorney (7:45)
RESOURCE. CENTER FOR THE ELDERLY
Peg Cullen and Richard Penley informed the Village
Board that the Resource Center is seeking contributions
from municipalities and townships to continue the "Serve
Our Seniors" program.
The consensus of the Village Board was to discuss
this item at a later date.
JFK BRIDGE RECONSTRUCTION
The Village Manager noted that to receive Federal
funding the stop signs on Kennedy at Brantwood must be
removed because those signs do not meet traffic warrants.
in addition, the Village Manager noted that the agreement
for Federal funding will appear on the April 9 Agenda.
The Village Board also discussed a recommendation by
the Village Engineer to reconstruct Kennedy Boulevard from
Brantwood to Cyprus. The consensus of the Committee was
for the road to be reconstructed at an additional cost of
$65,000.
The meeting was adjourned at 7:50 p.m.
c : President & Board of 'Trustees, Village Manager,
Assistant Village Manager, Administrative Assistant,
Administrative Intern, Village Clerk, Village Attorney,
All Department Heads