Loading...
HomeMy WebLinkAboutCOMMITTEE OF THE WHOLE - 03/26/1991 - RESOURCE CENTER FOR ELDERLY/JFK BRIDGE RECONSTRUCTION COMMITTEE OF THE WHOLE MEETING 3-26-9.1 7 P.M. PRESENT: C . Zettek, Village President M. Tosto, Village Trustee N. Czarnik, Village Trustee J. Petri, Village Trustee J. Bosslet, Village Trustee R. Chernick, Village Trustee D. Gallitano, Village Trustee ABSENT: NONE ,STAFF PRESENT: C. Willis, Village Manager G. Parrin, Assistant Village Manager R. Rummel, Administrative Assistant M. Pye, Assistant Village Engineer G. Knickerbocker, Village Attorney (7:45) RESOURCE. CENTER FOR THE ELDERLY Peg Cullen and Richard Penley informed the Village Board that the Resource Center is seeking contributions from municipalities and townships to continue the "Serve Our Seniors" program. The consensus of the Village Board was to discuss this item at a later date. JFK BRIDGE RECONSTRUCTION The Village Manager noted that to receive Federal funding the stop signs on Kennedy at Brantwood must be removed because those signs do not meet traffic warrants. in addition, the Village Manager noted that the agreement for Federal funding will appear on the April 9 Agenda. The Village Board also discussed a recommendation by the Village Engineer to reconstruct Kennedy Boulevard from Brantwood to Cyprus. The consensus of the Committee was for the road to be reconstructed at an additional cost of $65,000. The meeting was adjourned at 7:50 p.m. c : President & Board of 'Trustees, Village Manager, Assistant Village Manager, Administrative Assistant, Administrative Intern, Village Clerk, Village Attorney, All Department Heads