CAPITAL IMPROVEMENTS COMMITTEE
JUNE 10, 1999
';:00 PM
CHERNICK CONFERENCE ROOM
Present: Patton Feichter, Chair o
Trustee Petri, Member
Absent: Trustee Dill, Member
Staff: Asst. Village Mgr. Rummel
Deputy Fire Chief Clark
Training Coordinator Sullivan '
n
Oakton Street Fire Training Facility
o'
J
The Capital Improvements Committee met for the purpose of reviewing the Fire
Department's request for additional funding for the construction of the Fire Training
4—
Facility.
Staff explained the budgetary and construction cost information that provide the reasons
for the additional funding. These reasons include the fact that the actual bids/costs for 3N
the construction exceed the original cost estimates and also that contingency fees were L
not taken into consideration in the original estimate. In addition, there were code 9J
improvement requirements made at the direction of the Engineering and Community o
Development Department and the Metropolitan Water Reclamation District that were not a
originally included in the building design.
0
The total additional funding requested by the Fire Department was $450,000 based on a 3
revised total project cost of $1,200,000. This includes $300,000 for the additional
construction costs and $150,000 for the additional Symtron "fireplace" that was
previously approved by the Village Board of Trustees. A copy of the staff report is
attached.
The consensus of the Capital Improvements Committee was to recommend that the
Village Board increase the budget to $1 ,200,000 for the project and award the bids to
initiate construction. It was emphasized that the contractors be pre-approved.
0
The meeting adjourned at 3:20 PM.
C: President & Board of Trustees, Village Manager, Assistant Village Manager,
Assistant to the Village Manager, 'Village Clerk, Fire Chief, Deputy Fire Chiefs
� C3
0 �0
OAKTON STREET TRAINING FACILITY
I. BUDGET REQUEST DETAIL
Original BWC Construction Cost, 3-11-98 $455,000
Add, Symtron Live Fire Training Equipment Cost 400.000
855,000
Add, BWC Design/Construction Mgmt. Fees 95.000
950,000
Less, BWC/Symtron Construction Cosis Redundancies 100.000
850,000
Less, Second Fireplace Costs 150.000
700,000
Add, SCBA Air Compressor Cost 50.000
Training Facility Budget Request $750,000
ll. CONSTRUCTION FUNDS AVAILABLE
Training Facility Budget $750,000
Less, SCBA Air Compressor Cost 50.000
700,000
Less, BWC Design/Construction Mgmt. Fees 95.000
605,000
Less, Symtron Live Fire Training Equipment Cost 250.000
Construction Funds Available (reflects no contingency funds) $ 355,000
OAKTON STREET TRAINING FACILITY
III. CONSTRUCTION COST SUMMARY
BIDDER WORK ESTIMATE ACTUAL DIFFERENCE
(1-C4-99)
Fisher Const. General $440,000 $420,000 $20,000
Corkill Electric 26,118 46,000 (19,882)
Bartlett Mechanical 8,500 14,929 (6,429)
Doucette Sprinklers 8,250 7,750 500
Bert Young Plumbing 8,250 13,010 (4,760)
Underdrain -0- 10,000 (10,000)
Draft Pit -0- 26,700 (26,700)
Excavation =0_ 5.000 (5,000)
Total (Bid Estimate v. Actual) $491,118 $543,389 $(52,271)
Add,
BWC 5% Contingency Estimate 23,704 27.169 (3,465)
$514,822 $570,558 $(55,736)
Additional Costs:
Code Requirement Improvements 17,657 (17,657)
1%Contingency Increase 5,434 ( 5,434)
Smoke Machine Piping 16,050 (16,050)
Preliminary Elect/Plumbing Work 20.825 (20,825
Total Building Construction Costs $630,524 $(139,406)
-------- ---------
-------- ---------
OAKTON STREET TRAINING FACILITY
IV. TOTAL TRAINING FACILITY COSTS
Building Construction Costs $630,524
Symtron Fire Training Equipment 400,000
SCBA Compressor 50,000
Design, Construction, Mgmt. Fees 95.000
Total Training Facility Costs: $1,175,524
V. Additional Funds Requested
Total Training Facility Costs $1,175,524
Training Facility Budget 750.000
Additional Funding Reauest $ 425,524
VI. Variance Summary
Total Training Facility Cost Variance $ 425,524
Less, 2nd Fireplace 150.000
(previously approved but not included)
Construction Costs $275,524