PLAN COMMISSION MINUTES
January 6, 1993
Present: John R. Glass, Chairman
Fred Geinosky, Secretary
Charles Henrici
John Meyers
George Mullen
David Paliganoff
Paul Ayers
Absent: Tom Parker
Pat Feichter
Staff: Renee M. Farrell , Administrative Assistant
Earle Kracht, Building Inspection Supervisor
Petitioners: Reverend Schindel , Christus Victor Lutheran Church
Bob Gudmundson, Cowley, Gudmundson, Leder, LTD.
Chairman Glass called the meeting to order at 8:10 p.m.
Item A: Christus Victor Lutheran Church
Revised Landscaping Plan
Reverend Schindel stated that the revised plan contains additional
plantings of upright arborvitaes on the north end of the parking lot.
The Reverend stated that this type of plant provides the screening
needed to shield headlights from residential homes adjacent to the
parking lot. The Reverend further noted that the plantings on the
revised plan have been installed as shown.
Commissioner Paliganoff and Commissioner Meyers expressed
dissatisfaction regarding the quality and installation of the
plantings. In addition, Commissioner Paliganoff was disappointed on
the lack of sodding for the berm and the current conditions of weeds
growing on the berm.
Reverend Schindel stated that Bertholds Nursery and members of the
church performed the installation of the plantings. Reverend Schindel
also noted that the berm will be re-seeded and treated with weed killer
to terminate weed growth.
Commissioner Meyers stated that the installed plantings were
immature and insufficient to provide the necessary screening of the
parking lot. In addition, Commissioner Meyers stated that the church
should have approached the Village with the revised plan before
installing the plantings.
Chairman Glass stated that it was not the intention of the Plan
Commission to have the church provide mature plantings when the
original plan was approved.
Plan Commis(,n M- . .tes C
January 6, 1993
Page 2
After further deliberation Commissioner Ayers motioned to
recommend to the Village Board to approve the revised landscaping
plan. Commissioner Henrici seconded the motion. Upon voting, six(6)
AYES were counted with one(1) NAY from Paliganoff (Parker, Feichter
ABSENT) .
Item B: Super Kmart - Final Plat of Subdivision, Final Landscaping
and Screening Plan
Chairman Glass questioned Gudmundson if he had any problems in
complying with the twelve(12) requirements to the plat of subdivision
as outlined in Al Boffice's memorandum dated January 6, 1993.
Gudmundson stated that those twelve(12) items will be included on the
plat of subdivision.
Commissioner Mullen motioned to recommend to the Village Board to
approve the final plat of subdivision conditional upon revising the
plan to include the twelve(12) requirements as stated in Al Boffice's
January 6 memorandum. Commissioner Geinosky seconded the motion. Upon
voting, all AYES, (Parker, Feichter ABSENT) . The motion carried
unanimously.
Gudmundson then presented the final landscaping and screening
plan. Gudmundson stated that the plan shows the 5 to 7 foot berm on
the north and west side of the property as well as an eight(8) foot
fence on top of the berm. The fence will be provided with a gate to
allow for egress and ingress to both sides of the fence. The gate will
have a lock on the Kmart side of the fence to prevent trespassing.
Gudmundson noted that the fence is continuous and is supported by 12"
to 15" stilts where the berm slopes downward adjacent to the detention
basin.
Gudmundson also noted that the two(2) requirements from Boffice's
January 6 memorandum will be included on the final plan. Those
modifications include the extension of the fence terminations to
enclose the lot and clarify where the berm will be sodded or seeded.
Commissioner Meyers questioned the safety especially to children
where there is a oap under the fence. Commissioner Meyers inquired if
a barrier could be placed in the openina. Gudmundson stated that a
barrier could be provided that would allow the free flow of water.
Commissioner Henrici questioned the specific height of the berm
within the 5 to 7 foot parameter. Gudmundson stated that 70% of the
berm will have a height between 6 to 6 and half feet. The berm will be
close to 5 feet in height where the ground level is already high (close
to Biesterfield Road) . Gudmundson further noted that the variations in
the height of the berm will be gradual .
Commissioner Henrici questioned the height of the top of the fence
in relation tq the asphalt of the driveway. Gudmundson stated the
height will be approximately 10 to 11 feet.
Plan Commisk i M- .tes
January 6, 1993
Page 3
Commissioner Meyers asked where the berm will be seeded or
sodded. Gudmundson stated that the berm will be sodded on the
residential side of the fence and on the building frontages. The berm
will be seeded on the Kmart side of the fence behind the buildings.
Commissioner Henrici questioned if a variation is needed for the
eight(8) foot fence. Farrell stated that a variation is not needed as
the fence is considered screening and only needs approval as such.
A member from the audience questioned the type of fence to be
installed. Gudmundson stated that the type of fence will be clarified
on the plan.
After further deliberation, Commissioner Mullen moved to recommend
to the Village Board to approve the final landscaping and screening
plan conditional to the following revisions:
- to show the proper fence terminations;
- to clarify the sections of the berm that are
seeded or sodded;
- to indicate the type of wooden fence;
- to indicate the location of the gate; and
- to show a barrier in the opening under the
section of fence directly adjacent to the
detention basin.
Commissioner Paliganoff seconded the motion. The motion carried
unanimously (Parker, Feichter ABSENT) .
Adjournment:
Commissioner Mullen made a motion to adjourn the meeting.
Commissioner Henrici seconded the motion. The motion carried
unanimously (Parker, Feichter ABSENT) . Chairman Glass adjourned the
meeting at 9:30 p.m.
Respectfully submitted,
Renee M. Farrell
Administrative Assistant
el 1-8-93
C: Chairman and Members of Plan Commission, ZBA Chairman, Village
President, Board of Trustees, Village Clerk, Village Manager,
Assistant Village Manager, Administrative Assistant, Administrative
Intern, Director of E/CD, Director of Public Works, Fire Chief,