CAPITAL IMPROVEMENT COMMITTEE
MEETING MINUTES James P. Petri Public Works Facility December 12, 2019
9:00 AM
Present: Trustee Czarnik, Chairman Trustee Franke Trustee Schmidt
Staff: Matt Roan, Deputy Village Manager Colby Basham, Director of Public Works Brian Lovering, P.E., Chief Engineer Jeff Maczko, P.E., Senior Engineer
Chairman Czarnik called the meeting to order at 9:05am The Committee reviewed the proposed street maintenance program, which includes the resurfacing
of 9.75 miles of streets and the rehabilitation of curb, sidewalk and ADA compliant curb ramps. The proposed 2020 MFT program (4.38 Miles) has an estimated construction cost of $1,503,645. The Village has also reserved $185,000 of MFT funds for roadway patching and concrete work at various locations throughout the Village. The proposed 2020 Business Park program (2.94 Miles), which has an estimated construction cost of $1,239,120 will be funded utilizing funds from the Business
Leaders Forum account. Also in the upcoming year, the intersection of Nerge Road and Rohlwing Road scheduled to be resurfaced. Project limits for this improvement include Nerge Road from Mitchell Trail to Devon Avenue, and Rohlwing Road from Devon Avenue to Huntington Drive. Village staff has secured
Federal Surface Transportation Program (STP) funding (80% of the construction cost), and remainder of the construction will be funded by local funds. This project is set to begin in April when weather allows.
In addition to the 2020 MFT program, Vermont Drive (Plum Grove Road to Gibson Drive) and Gibson Drive (Biesterfield Road to Julie Drive) is proposed to be rehabilitated using a process called Full Depth Reclamation (FDR). These existing roads have sections of pozzalonic base, which has reached the end of its life cycle resulting in severe cracking and base failure. Full reconstruction of
these sections of the roadway will be challenging due the amount of driveway aprons and lack of on
street parking. Full Depth Reclamation will allow the existing pavement and base course to be ground in place, recycled, and reused as a new, stronger base course. Residents will have access to their driveways at the end of each day during the FDR process. The proposed Vermont Drive / Gibson Drive Rehabilitation will be completed utilizing funds from Capital Project Fund.
The Committee also discussed continuing pavement rejuvenation as a new part of the overall street maintenance program. The proposed streets to be rejuvenated in 2020 are all streets that were resurfaced or rehabilitated in 2019. The proposed 2020 Pavement Rejuvenation Program includes a
total of 9.44 miles of Business Park and residential streets, and will be completed utilizing funds from the General Fund (Streets) and BLF accounts.
Lastly, the Committee discussed standing water on Village sidewalks. Staff informed the Committee that the engineering consultant under contract with the Village for drainage will be making a presentation to the Board regarding this subject, as well as rear yard drainage, in February 2020. The Committee approved the proposed 2020 MFT Street Maintenance Program as present by Staff.
Chairman Czarnick adjourned the meeting at 10:43am.
C: Mayor and Board of Trustees Village Manager Deputy Village Manager Village Clerk
Director of Public Works
Director of Community Development
12/10/2019 1 of 2
Street Begin End Last
Resurfaced
Length
(ft)FY20-21
$65.00Avon Road Penrith Ave Milbeck Ave 2006 1,147 74,555.00$
Brantwood Court Brantwood Ave End 2006 292 18,980.00$
Brantwood Place Brantwood Ave End 2006 173 11,245.00$
Creighton Avenue Keswick Rd John F. Kennedy Blvd 2003 283 18,395.00$ Grassmere Road Penrith Ave Brantwood Ave 2008 978 63,570.00$ Keswick Road Penrith Ave Brantwood Ave 2003 1,500 97,500.00$ Milbeck Avenue Keswick Rd Grassmere Rd 2006 882 57,330.00$
Milbeck Court Grassmere Road End 2003 428 27,820.00$
Penrith Avenue Keswick Rd Brantwood Ave 2006 1,651 107,315.00$
Shelly Road Arlington Heights Rd Brantwood Ave 2006 443 28,795.00$ Lindale Street Wildwood Rd End 2002 225 14,625$ Wildwood Road Oakton Ave E. Higgins Rd 2009 1,975 128,375$ Charing Cross Road W. Elk Grove Blvd Ridge Ave 2001 3,343 217,295$ Edgeware Road Charing Cross Rd Ridge Ave 2007 1,385 90,025$
Middlebury Ln Tower Ln Victoria Ln 2007 1,820 118,300$
Sussex Court Tower Ln Middlebury Ln 2007 1,064 69,160$
Beisner Road Gloucester Dr Winston Dr 1998 1,124 73,060$ Bradford Circle Winston Dr End 2006 463 30,095$ Lakeview Circle Winston Dr End 2006 468 30,420$ Parkview Circle Winston Dr End 2006 465 30,225$
Ruskin Circle Winston Dr End 2008 489 31,785$
Ruskin Drive Winston Dr Winston Dr 2008 2,535 164,775$
1,503,645$
Street Begin End Last
Resurfaced
Length
(ft)FY20-21
$80.00Chase Avenue Tonne Rd Touhy Ave 2007 4,974 397,920$
Morse Avenue Tonne Rd Busse Rd 2003 5,248 419,840$
Lunt Avenue Tonne Rd Busse Rd 2004 5,267 421,360$
1,239,120$
1,255,255$
1,870,000$
5,868,020$
BUSINESS PARK PROGRAM ESTIMATE (2.94 Miles)
NERGE ROAD RESURFACING (STP) (0.83 Miles)
VERMONT LANE & GIBSON DRIVE REHABILITATION (1.60 Miles)
TOTAL ROADWAY IMPROVEMENTS (9.75 Miles)
PROPOSED 2020 ROADWAY MAINTENANCE PROGRAM
BUSINESS PARK STREET RESURFACING (BLF)
Cost per LIN FT based on Previous Year's Program (For Similar Rated Street)
RESIDENTIAL STREET RESURFACING (MFT)
Cost per LIN FT based on Previous Year's Program (For Similar Rated Street)
RESIDENTIAL PROGRAM ESTIMATE (4.38 Miles)
12/10/2019 2 of 2
PROPOSED 2020 ROADWAY MAINTENANCE PROGRAM
Street Begin End Length (ft)FY20-21
$1.00Ash St Elmwood Ln Carswell Ave 283 786$ Brynhaven St Woodcrest Ln Wildwood Rd 865 2,403$ Brynhaven Ct Brynhaven End 145 403$
Carswell Ave Clearmont Dr Cedar Ln 2,082 5,783$
Cedar Ln Clearmont Dr Victoria Ln 2,765 7,681$
Clover Hill Ct Wellington Ave End 530 1,472$ Clover Hill Ln Montego Ct Wellington Ave 636 1,767$ Grosvener Ln Tower Ln Victoria Ln 1,912 5,311$ Grosvener Ct Grosvener Ln End 215 597$ Grove Dr Perrie Dr Perrie Dr 1,170 3,250$
Hartford Ln Tonne Rd Maple Ln 2,063 5,731$
Maple Ct Cedar Ln End 780 2,167$
Oak St Laurel St Tower Ln 933 2,592$ Perrie Dr Landmeier Rd Kent Ave 2,900 8,056$ Tower Ln Elk Grove Blvd Ridge Ave 2,115 5,875$ Wellington Ave Somerset Ln Clover Hill Ln 2,965 8,236$
Wilshire Ave Birchwood Ave Carswell Ave 1,160 3,222$
Easton Lane West Glenn Trail End 2,840 7,889$
Normandy Court Easton Lane End 750 2,083$ Columbia Court Biesterfield Road Easton Lane 180 500$ McDevitt Circle White Trail Court End 175 486$ Shepard Circle White Trail Court End 175 486$
Inverness Court University Lane End 750 2,083$
Doral Court University Lane End 500 1,389$
Minot Court Dakota Drive End 320 889$ Bismark Court Dakota Drive End 400 1,111$ Geneva Circle Wisconsin Lane End 140 389$ Madison Court Wisconsin Lane End 200 556$
Racine Court Wisconsin Lane End 150 417$
Omaha Circle Nebraska Drive End 125 347$
Arthur Ave Devon Ave Busse Rd (1200' west)3,980 16,362$ Crossen Ave Oakton St Higgins Rd 1,321 5,431$ Pratt Blvd Tonne Rd Busse Rd 4,200 17,267$ Kent Ave Perrie Dr Oakton St 918 3,774$ Lively Blvd Devon Ave Landmeier Rd 7,200 42,075$
University Ln Vermont Dr Plum Grove Rd 2,000 8,320$
177,184$
PAVEMENT REJUVENATION (Reclamite)
Cost per SQ YD based on Previous Year's Program
TOTAL PAVEMENT REJUVENATION PROGRAM (9.44 Miles)
ROHLWINGRDNERGERD BEISNERRDO M A H A C IRGENEVA CIR
W ELLINGTONAV E
BRYNHAVEN CT
RACINECIR PERRIE
D
RSHEPARD CIRCHARINGCROSSRD
GIBSONDR
BRANTWOOD PL
COLUMBIA CTMADISON CT WILDWOODRDSTOWE CIR
HARTFORD L NGROSVENERCTMAPLE CTLINDALE ST
MCDEVITT
CIR
KESWIC K RD
Y ALE CT
PENRITH
AVEC E D A RLN
CARSWELL AVE
TOWER LN
MID
DLE
B
U
R
Y LN
ASH STCREIGHTON AVEGRAS SMERER DMILBEC
K
AVE
BRANTWOOD CT
MIN
O
TCT
NORMAN DYCTLIVELYBLVDLIB E R TYCTRUSKIN DR
UNIV
ERSIT
Y
LNBIS
MA
R
KCTEASTO NL N
MILBECK CT
SHELLEY RD
BRADFORD CIR
PARKVIEW CIRLAKEVIEW CIR
RUSKINCIR
DO RALC T
CLOVERHILL CT GROSVENERLNBRYNHAVEN ST
CLOVERHILLLN
CO N C O RDLNINVERNE SSCT KENTAVE
OAK STNEWBE RRYDR
S
U
S
S
E
X
C
TE DGEWA R E
R DAVON R D
WIL
S
HIREAVE GROVEDR CROSSEN AVEARTHUR AVE
PRATT BLVD
MORSE AVE
LUNT AVE
CHASE AVE
VERM ONTDR
PROPOSED 2020 ROADWAY MAINTENANCE PROGRAM ¯
Residential StreetResurfacing (MFT)
Business ParkResurfacing (BLF)
Nerge RoadResurfacing (STP)
Vermont Lane andGibson DriveRehabilitation
PavementRejuvenation(Reclamite)