HomeMy WebLinkAboutPLAN COMMISSION - 11/05/1986 - BONDIOLI/WINSTON GROVE RESUB. Minutes
ELK GROVE VILLAGE PLAN COMMISSION
Date: Wednesday, November 5, 1986
Location: Council Chamber
901 Wellington Avenue
Members Present: Members Absent:
John Glass, Chairman Frederick Geinosky
Leah Cummins, Secretary
Clark Fulton
George Mullen
David Paliganoff
Staff Present:
Thomas Rettenbacher, Building Commissioner
John Coakley, Administrative Intern
Others Present:
Donna Bondioli, owner of subject property
Donald Patelle, Industrial Real Estate Broker
S. J. Lakeford, Attorney representing Bondioli
The meeting was called to order at 8:13 p.m. j
Bondioli: Rezoning
(Located on Landmeier Road west of
Busse Road - Kearn Engineering)
Lakeford stated that the petitioner is requesting rezoning of
a 1.2 acre parcel from B-3 to I-1. He said a multi-use industrial
building is planned for the lot. He further noted that the front
135 feet of the property is already zoned I-1.
Donna Bondioli stated that a 25,000 square foot combination
office and industrial building will be constructed if the rezoning
is granted. The building will consist of approximately 11 units of
I
various sizes. She said the existing Kearn Engineering building
would be demolished and removed.
Donald Patelle stated that the proposed usage would be the
highest and best use for the land because the Village would benefit
through the tax revenue. He noted that the construction cost would
be $800,000.
George Mullen inquired about tenants for the building. Patelle
responded that no tenants had been signed up yet, but that there
should be no difficulty renting the facility. He also said that
Bondioli would retain ownership of the facility once it is built.
Bondioli responded to David Paliganoff's question regarding
the type of tenants by stating that they would include sales
representatives, machine shop, and distributors. She based her i
answer on the types of businesses that have contacted her about
the facility.
i
i
i
Plan Commission Minutes - 2 - November 5, 1986
Bondioli : Rezoning (continued)
Patelle stated that they want to begin construction this fall
and finish in the Spring of 1987. He then described the zoning of
the properties surrounding the Bondioli parcel. To the east is B-3
zoning, I-2 zoning on the south and southeast, and I-1 zoning to the
north and west.
Leah Cummins inquired about the landscaping plan for the property.
Patelle responded that they would put in whatever the Village requires.
He said that some combination of grass, bushes and trees would be used
to make the building attractive.
The public hearing was closed at 8:49 p.m.
Following further discussion, Leah Cummins made a motion to
recommend rezoning and Clark Fulton seconded it. The vote for
approval passed unanimously.
Winston Grove: Section 23B Resubdivision No. 5 -
Plat of vacation
Following discussion and review of the plat, Leah Cummins
motioned to recommend approval of the plat of vacation and George
Mullen seconded it. The vote for approval passed unanimously.
Following discussion of future meetings, the meeting was adjourned
at 9:11 p.m.
Respectfully submitted,
I
J n M. Coakley
Administrative Intern
i
ms
c: Chairman & Members of Plan Commission, village President,
Board of Trustees, Village Clerk, Village Manager, Assistant j
Village Manager, Administrative Assistant, Administrative
Intern, Building Commissioner, Village Engineer, Director
of Public Works, Fire Chief, Deputy Fire Chief, Village
Attorney, Park District, NWMC.
I
i
I
I
I